149. The authorization holder must prepare a daily report of the construction work and keep it in the temporary work areas.
The daily report must contain all the elements applicable to the declared day including, in particular,(1) the name and contact information of the holder and the authorization number;
(2) the number of welds carried out;
(3) the number of portions of lines installed and the elements contained therein;
(4) the result of the inspections carried out;
(5) the operational problems encountered and the corrective measures taken or planned;
(6) the indication of any event that disrupted the planned progress of the work; and
(7) any other information or document deemed necessary by the Minister.
1253-2018O.C. 1253-2018, s. 149.